Vulcan Energy Resources has commenced civil construction works for its commercial Lithium Extraction Plant (LEP), part of its so-called Project Lionheart, located in Germany's Upper Rhine Valley.
The plant will produce high purity lithium chloride intermediate from geothermal brine wells with geothermal energy generated from the same brine used to power operations.
The LEP will use Vulcan’s in-house, proprietary VULSORBTM technology to extract lithium chloride as part of its direct lithium extraction process.
This will then be converted to battery grade lithium chemicals in a final step at the company’s downstream lithium chemical plant in Frankfurt-Hoechst, for onward sale to battery and electric vehicle customers focused on Europe.
“Lionheart continues to build momentum, with our team delivering construction on schedule and within budget,” said Vulcan Energy’s Managing Director and CEO, Cris Moreno.
“The start of civil construction works at the LEP now completes all major execution milestones we set for 2026 and represents another important step forward in bringing Lionheart into production.”
Civil activities follow the already completed early bulk earthworks on the site and precede the next construction stage, comprising the erection of buildings and arrival of process equipment for assembly.
Civil construction will include preparation of key foundations and concrete works for the buildings, process equipment, utilities and tank farm, and building out road infrastructure and drainage networks.
Lionheart — Vulcan Energy’s first phase of production — is a key project for Europe’s energy and critical raw material resilience, according to Moreno.
The integrated, low-cost lithium and renewable energy project is targeting production capacity of 24,000 tonnes of lithium hydroxide monohydrate (LHM), enough for around 500,000 electric vehicle batteries per annum, alongside 275 GWh of renewable power and 560 GWh of heat per annum for local consumers, over an estimated 30-year term.
“With few new lithium projects in the Western world under construction, and Lionheart the only one of scale in Europe, we believe the project’s strategic importance continues to grow,” said Moreno.
“We will enter 2027 with a clear focus: maintain execution discipline, advance construction and deliver a critical domestic source of lithium to strengthen Europe’s battery supply chain resilience and industrial competitiveness.
”Lionheart is under construction with take-or-pay lithium offtake contracts and targets first production in H2 2028.